
Construction Updates
Sept. 5, 2025
In the past week, crews made steady progress with roofing (65%), exterior wall framing (50%), and nearly finished curbs and interior wall layouts (both around 90%). Awning steel and roof framing were completed, and grout was placed under base plates. In the coming week, work will continue on roofing, curbs, backfilling, interior wall layouts, and exterior wall framing.
August 29, 2025
This week we saw progress on the roof awnings, curb, exterior wall framing and layouts for both interior and exterior walls. Next week, work will continue on these things plus sewer line and roof framing will begin as well.
August 22, 2025
Last 7 Days:
Roofing installed - 50%
Structural steel for awnings - 25%
Backfill behind curb
Curb - 90%
Layout for exterior and interior walls
Next 7 Days
Insulation and roof panels expected to continue
Exterior wall framing expected to start
Structural steel for awnings expected to continue
Curb expected to continue
August 15, 2025
There were lots of delays due to rain this week, but the curb around pond was poured. Next week, roofing panels will continue to be installed and exterior wall framing and steel for awnings are expected to be begin construction.
August 8, 2025
This Past Week
Curbs poured from the dumpster pad to CB-4
Sewer prep began
Silt fence installed for erosion control.
Next Week:
Work on the curbs will continue
They’ll begin installing insulation and roof panels
Framing the outside walls of the building will get started
August 1, 2025
This week and next the exterior structural steel will continue to be installed. Curb and sewer installation will begin soon.