Sept. 26, 2025

This past week, big strides were made! The roof is now 70% complete, interior wall layouts are finished, and electrical conduit for data boxes and outlets is fully installed. Exterior walls and sheathing continue to rise, while faux column framing and stormwater work have just begun.

Looking ahead, roofing, framing, and curb work will keep moving forward. Mechanical ductwork and units are also set to begin, marking an exciting new phase in the project!

Construction Updates

Sept. 19, 2025

This past week, roofing reached 70%, backfill and curbs neared completion, and interior wall layout moved to 90%. Exterior wall framing advanced to 65%, with initial work on sheathing, faux columns, and mechanical systems underway. In the coming week, crews will continue these efforts while also beginning installation of the storm water line from the pond.


Sept. 12, 2025

This past week roofing, curb work, interior wall layout, and exterior framing all made steady progress, with roof lining and braces completed. In the coming week, crews will continue roofing, backfilling, curb work, wall framing, and Dens Glass (weather resistant wall board), while also starting the storm water line and faux column framing.


Sign the Steel Event- Sept. 7

On Sunday, September 7, with beautiful weather, over 60 people came to our new church building to cover the steel structure and concrete floor with blessings. Scripture verses were written on each major support column and much of the framing, while our artists added beautiful writings to the floor. The next day, the construction team shared how encouraging it was to see all the signing—and even added Scripture to the top steel themselves! How comforting to know that when we move into our new building, its very foundation and walls will be covered in the Word of God.



Sept. 5, 2025

In the past week, crews made steady progress with roofing (65%), exterior wall framing (50%), and nearly finished curbs and interior wall layouts (both around 90%). Awning steel and roof framing were completed, and grout was placed under base plates. In the coming week, work will continue on roofing, curbs, backfilling, interior wall layouts, and exterior wall framing.


August 29, 2025

This week we saw progress on the roof awnings, curb, exterior wall framing and layouts for both interior and exterior walls. Next week, work will continue on these things plus sewer line and roof framing will begin as well.