Construction Updates
Below are weekly updates about our new building located at:
980 North White Street
Wake Forest, North Carolina
January 9, 2026
Current Progress:
This past week saw significant progress toward closing out the building's core systems and exterior. We have nearly completed the electrical conduit, mechanical ductwork, and insulation, with all systems sitting at approximately 98% completion. Critical infrastructure, including the mechanical line sets, stage ramp framing, and dumpster corral walls, has reached 100%. On the exterior, the sidewalks are finished, and the stone veneer and window installations are nearly wrapped up at 95%. Inside the sanctuary, drywall hanging is moving quickly at 92%, while the finishing phase has surpassed the halfway mark. We also made significant strides in the site work, completing a substantial portion of the storm pipe installation and grading 80% of the parking lot subgrade.
Looking Ahead: The Next 7 Days
The primary focus for the coming week is achieving conditional power, which will involve intensive coordination between the electrical and mechanical teams. In preparation for the parking lot paving, we will begin laying stone for the graded areas while continuing storm water and landscape grading. Inside the building, the AV contractor is scheduled to finish their rough-in mounting by Tuesday, clearing the way for dryfall paint application on Wednesday. We will also begin several finish-level tasks, including the installation of all interior door frames and bathroom wall tiles. Finally, our team will measure for the fabrication of metal railings and gates to ensure these custom components remain on schedule.
January 2, 2026
Current Progress
We have seen significant progress on our building site this week. Most of the parking lot has now been surfaced with stone, and the storm drainpipe installation is moving steadily forward. On the building itself, the stone veneer is looking wonderful and is nearly complete. Inside, our teams are continuing to work diligently on the remaining drywall, as well as the essential mechanical and electrical systems that will power our new facility.
Looking Ahead
Next week promises to be another productive period as the contractor begins the transition toward interior finishing. Crews will start sanding and priming the walls to prepare them for paint, and we expect to finalize both the parking lot stone and the exterior stone veneer. Additionally, work will continue on the storm drainage system and the mechanical and electrical installations. We are also excited to see the first door frames being installed, marking another great milestone in our journey toward completion.
December 26, 2025
No written update but here are some additional photos/video from the past week:
December 19, 2025
Over the past week, major behind-the-scenes work has continued to move the building closer to completion. Most of the electrical, mechanical, and plumbing systems above the ceiling are nearly finished. Sidewalks on the north and west sides are complete, with the south side almost done. Drywall installation is well underway, and exterior windows and storefronts are nearly finished. We’ve also made good progress on the parking lot area, entrance curb, and even began installing the stone veneer on the outside of the building.
In the coming days, work will focus on preparing and stoning the parking lot, continuing interior wall framing, and finishing drywall installation. Mechanical, electrical, plumbing, and stormwater work will continue above the ceiling. Grading for curbs and landscaping will move forward, and construction will begin on the walls around the dumpster area. Overall, the building is steadily taking shape inside and out!