Construction Updates

August 8, 2025

This Past Week

  • Curbs poured from the dumpster pad to CB-4

  • Sewer prep began

  • Silt fence installed for erosion control.

Next Week:

  • Work on the curbs will continue

  • They’ll begin installing insulation and roof panels

  • Framing the outside walls of the building will get started


August 1, 2025

This week and next the exterior structural steel will continue to be installed. Curb and sewer installation will begin soon.


July 25, 2025

It’s been a very exciting week at the site as the steel has been constructed!