
Construction Updates
August 8, 2025
This Past Week
Curbs poured from the dumpster pad to CB-4
Sewer prep began
Silt fence installed for erosion control.
Next Week:
Work on the curbs will continue
They’ll begin installing insulation and roof panels
Framing the outside walls of the building will get started
August 1, 2025
This week and next the exterior structural steel will continue to be installed. Curb and sewer installation will begin soon.
July 25, 2025
It’s been a very exciting week at the site as the steel has been constructed!