
June 20, 2025
The conduits for underground electrical wiring and the sanitary drain pipe under the building have been installed and inspected by the town. The concrete piers will be poured this coming week.
June 13, 2025
The concrete has been poured in footings, rebar has been set for piers and underground plumbing work has begun. Next week, underground plumbing and electrical work will be done and concrete for pier will be poured.
June 6, 2025
The column footings including the rebar have been completed. Next week, the town will inspect the rebar. Focus expects to start pouring column footings and piers on Tuesday.
July 11, 2025
The concrete has been poured and the steel has been delivered! Over the next few weeks, we will start to see the steel framing constructed.
July 4, 2025
There are lots of exciting things happening on the site! This week there was prep work done for the curb and gutter, for the parking lots and for the concrete slab. Due to rain, the concrete is now scheduled to be poured Tuesday, July 8. Steel will be delivered on Thursday and Friday next week as well!!
Construction Updates
June 27, 2025
Underground work is mostly finished, including electrical and storm water systems. The foundation piers are poured, and prep for the slab, parking lot, and curbs is well underway. Next week, work will continue on preparing the ground for the concrete slab, storm water system, curbs, gutters, and parking lot. Most underground work is wrapping up, and things are steadily moving forward.
May 30, 2025
The rain prevented much from happening this week but the footings are ready to install soon for the building pad!
May 23, 2025
This week a survey was completed for the column placements for the building. Grading and piping continued to make progress. Next week, underground utilities are expected to begin and footings placed for the foundation!
May 16, 2025
This week there was a pre walk through meeting with electrician, plumber and concrete contractors. No onsite work occurred due to rain and poor site conditions. Building foundation work will begin soon!
May 9, 2025
Storm drainage pipe has been installed and large piles of dirt have been removed from the property. Preparations are being made to pour concrete curb and gutter.
May 2, 2025
Storm drain piping is making good progress. The site is continuing to get cleaned up and new suitable structural fill has been delivered and will continue being spread. In the next week, they will continue grading, working on storm water and getting ready for underground utilities.
April 25, 2025
Grading is close to wrapping up. Storm water pipes and structures are continuing to be installed. The parking lot stone and curb and gutter will be installed soon and they will be preparing the building pad and foundation soon as well!
April 18, 2025
Grading is 80% complete. Storm water work and installation in progress in photos.
April 4, 2025
The grading is 75% complete! The building pad has been created, compacted and tested as they prepare to lay the foundation soon! Storm water work and grading will continue in the next week.
March 28, 2025
The grading/compacting will continue this coming week as well as installing storm pipe and some utilities.
Anticipated April Schedule:
Week of 4/7 : Focus will begin laying the building’s foundation, widening N White Street, and putting in the curb, gutter, and stone for the parking lot.
The foundation should be finished by the end of April. The concrete takes 1 month to gain its strength in time for the steel to be erected in mid-June.
March 21, 2025
Grading will continue through the next week. Pray for good weather and good soil conditions.
Groundbreaking Ceremony
What a wonderful celebration we had Saturday, March 8 at our church building’s
Groundbreaking Ceremony!
New Church Logo
From schools to rented spaces and even baseball parking lots, our church has met in a number of spaces over the years. Now, in 2025, God is giving us a permanent home on North White Street in Wake Forest! With this new location, we have updated our branding as well. This new logo represents: our history—in the Cross of Christ, always our central focus; our heritage—in our denomination, the Presbyterian Church in America; and our hope—in bold color and stately script, to show our resolve to clearly proclaim the Gospel to our community. Stay tuned with construction updates and opportunities to be involved.